(5) there shall be specific provisions for the change and change procedure of technical documents. Generally, the examination and approval of the change shall be carried out by the original examination and approval unit of the technical document. When other units examine and approve, they shall obtain the relevant data on which the original examination and approval unit is based.
1. Detection process
(1) before the test, check whether the sample or test piece is in good condition, whether the function and accuracy of the instrument and equipment meet the requirements, and whether the environmental technical conditions meet the technical requirements of the test.
(2) start the testing, and require the testing personnel to carry out the testing in accordance with the specified testing procedures and procedures.
(3) the inspection personnel shall make inspection records and ensure the accuracy of the recorded data.
(4) in case of edge data close to the qualified limit in detection, necessary repeated detection shall be carried out to verify the accuracy of detection data.
(5) at the end of the test, the technical status and environmental technical conditions of the instrument and equipment shall be checked. In case of any abnormality, the cause shall be found out and the reliability of the test results shall be verified.
2. Handling of abnormal conditions during detection
(1) in case of abnormal distribution of test data, the cause shall be found out and the test can be continued only after correction.
(2) when the detection results are affected by external interference (such as power failure, water outage, etc.), the detection personnel shall stop the detection and re detect after eliminating the interference. The original test data is invalid and the interference is recorded.
(3) if the detection is interrupted due to the failure of the instrument and equipment, the original detection data will be invalid. After troubleshooting, retest can be conducted only after the calibration is qualified.
(4) in the process of testing, if it is found that the sample or test piece is damaged or contaminated, and the correct test data cannot be obtained, the standby sample shall be used or the test sample shall be re sampled, and the test data of the later shall prevail.
3. Quality control by computer
When using computer to collect, process, calculate, record, report and store test data, necessary quality control shall be carried out to ensure the reliability and integrity of test data. The specific requirements are as follows.
(1) the operation of computers shall be carried out under the special responsibility system, and shall not be cross used without approval.
(2) an account shall be established for the storage medium of test data, and special personnel shall be responsible for proper management. It is not allowed to randomly place or contact unauthorized persons, so as to prevent artificial modification of test data.
(3) the first test and data processing results of the product shall be compared by other methods such as manual calculation to verify the correctness of the computer test.
(4) if necessary, the computer shall be equipped with uninterruptible power supply of appropriate capacity to prevent the loss of detection data in case of power interruption.
(5) to prevent computer virus infection, do not use unknown floppy disk, U disk or other storage media.
(6) the inspector shall sign on the original record, and the original record with multiple pages shall be stamped with the seal on the perforation for preservation.
The test record is the objective evidence of the test results, the basis of analyzing the problems and tracing the history, and the important basis of taking corrective and preventive measures, so the test record is a very important basic work. There shall be specific regulations on the format, identification, filling, check, change and filing of inspection records.
(1) the test records shall be true, accurate, complete and clear, and the blank items shall be marked with a slash.
(2) the format and content of test record shall be reasonably prepared according to different requirements of different test objects, generally including the following contents.
① sample name, specification and model, quantity, sample number and technical basis of the test.
② main instruments and equipment, environmental technical conditions (such as temperature, humidity, etc.).
③ technical reference value and actual measurement value specified in the test item.
④ necessary calculation formula and results.
⑤ the abnormal situation occurred in the detection and the countermeasures.
⑥ inspection time, and signatures of inspectors and verifiers.
⑦ the number and number of pages of the test record.
(3) in case of wrong value recorded in the test record, it shall be corrected in time. The method of correction is to draw a horizontal line on the wrong value, fill in the correct value above or below it, and affix the seal of the person who made the change. The change can only be made by the testing recorder, and no other person can replace the change. It is not allowed to record with pencil or change with correction fluid.
(4) the test record shall be signed by the tester and the checker to show that they are responsible for the record.
(5) data records shall conform to the provisions of error analysis and relevant technical standards.
0577-68523555
Address: Building 41,Wanyang Zhongchuang City,Qianku,Cangnan,Zhejiang Province
Fax: 0577-68520555
E-MAIL:sales@zjmdpackage.com
Copyright: Dongguan Marriott Packaging Co., Ltd. technical support: Gece marketing Disclaimer